The indoor pool will be closed beginning April 2, 2024, and work is estimated to be completed by May 13, 2024.

The tentative work schedule is as follows:

Project Stage Dates
Preparation April 2 – 5, 2024
Demolition April 8 – 12, 2024
Tiling April 15 – 19, 2024
Clean up, prep work for pebble, misc. April 22 – 26, 2024
New PebbleScheen applied April 29 – May 3, 2024
Final clean & water treatment May 6 – 10, 2024
Project completion May 13, 2024

The outdoor pool will be opened to the public while work is being performed on the indoor pool

Beginning April 8, 2024, the hours of operation for the outdoor pool will be 10 a.m. – 6 p.m. daily. If you have any questions or concerns, please contact the Parks & Recreation Department at 928-639-3200.


be the first to know, events,be the first to know, events,

Don’t Miss Another Event!





Source link
Staff , www.signalsaz.com
Signals AZ , 2024-03-31 00:00:41
Categories: Cottonwood,cottonwood,Cottonwood Recreation Center,pool closure,Pool work
Tags:

Share this Article
Leave a comment